NORTH BERGEN, NJ — November 20, 2026 — Construction of the $16 billion Hudson Tunnel Project has reached another milestone, with a second massive tunnel boring machine beginning excavation beneath the New Jersey Palisades.
Both tubes of the new rail tunnel are now under construction, marking an important step toward expanding rail capacity between New Jersey and New York City.
New Jersey Governor Mikie Sherrill highlighted the progress Friday, describing the launch of the second machine as another step toward more reliable transportation for commuters.
The Gateway Development Commission announced the milestone on November 18, confirming that the second machine had begun excavating the southern tunnel tube. The first machine started work on the northern tube in October.
Two Massive Machines Working Beneath the Palisades
The two machines are excavating parallel tunnels between North Bergen and the Hudson County Access Shaft near the border of Hoboken and Weehawken.
Each will construct approximately 5,100 feet of tunnel through the Palisades before reaching the access shaft.
The machines are enormous pieces of engineering equipment. Each has a cutting head measuring 28 feet, 8 inches in diameter, with additional machinery extending roughly 500 feet behind it. Each weighs more than 1,680 tons.
They are designed to cut through hard rock while simultaneously installing reinforced concrete segments that form the permanent tunnel lining.
By November 18, the first machine had already advanced approximately 400 feet and installed more than 60 rings of concrete lining.
The Palisades excavation phase is expected to take approximately one year, including scheduled maintenance periods.
Once that section is completed, the machines will be removed and replaced with another pair specifically designed for the different ground conditions beneath the Hudson River.
Excavation beneath the river is currently planned to begin in 2028.
Why the Gateway Project Matters
The Hudson Tunnel Project is one of the largest transportation infrastructure investments in the United States.
Its central objective is to build two new rail tunnel tubes beneath the Hudson River and rehabilitate the existing North River Tunnel, which has carried trains between New Jersey and Manhattan for more than a century.
The existing tunnel, opened in 1910, remains a critical connection for NJ Transit and Amtrak passengers traveling to and from New York Penn Station.
The new tunnels are intended to provide additional capacity and allow the older tunnel to undergo major rehabilitation without shutting down the entire rail connection.
For commuters, the project promises a more dependable transportation system and fewer disruptions caused by infrastructure problems.
However, those benefits will depend on completion of the remaining construction phases.
A Major Construction Milestone
The project involves multiple construction contracts and complex engineering work on both sides of the Hudson River.
The Palisades Tunnel section is being built by a joint venture involving Schiavone Construction, Lane Construction, and Dragados. The Port Authority of New York and New Jersey is overseeing the work in partnership with the Gateway Development Commission.
The launch of the second machine means both new tunnel tubes are now being excavated simultaneously.
While significant construction remains, the milestone represents visible progress on a transportation project that will affect hundreds of thousands of rail journeys throughout the New York–New Jersey region.
For New Jersey commuters who depend on rail service into Manhattan, the most important result will ultimately be whether the investment delivers the greater reliability and capacity the region has sought for decades.